KRP Phase 3 – Block E1

Case Study

Project Address

Kings Road Park,
Block E1,
SW6 2FR

Services

DMC Walling provided a fully integrated design, supply and installation service, including Curtain Walling, Cladding Systems, Copings, Rainwater Pipe Systems, Main Entrances, Architectural Louvres and Sunray doors

Timeline

November 2024 – June 2025
(6–8 months)

Case Study: Residential Façade at Kings Road Park, London

Project Overview: DMC Walling was appointed by St William Homes to deliver a complete, high-performance façade solution for the residential development at Kings Road Park, Phase 3 – Block E1. The project demanded precision engineering, seamless coordination, and exceptional finish quality to meet the architectural vision and performance requirements of a premium London development.

Location: Kings Road Park, Block E1, SW6 2FR

Project Duration: November 2024 – June 2025 (6–8 months)

Scope of Work: DMC Walling provided a fully integrated design, supply and installation service, including:

  • Curtain Walling
  • Cladding Systems
  • Copings
  • Rainwater Pipe Systems
  • Main Entrances
  • Architectural Louvres
  • Sunray doors


Project Description:

The project comprised the delivery of a high-quality building envelope solution, incorporating the design, manufacture, supply, and installation of a comprehensive range of façade and external envelope systems. DMC Walling provided an integrated service covering curtain walling, cladding systems, copings, rainwater pipe systems, main entrance assemblies, architectural louvres, and Sunray doors. The works were executed to meet the architectural intent, performance requirements, and durability standards, ensuring a cohesive, functional, and visually striking external façade.

Services Provided:

External Works:

From concept through to completion, DMC Walling took full ownership of the façade package, ensuring certainty in delivery, quality, and performance.

  • Design & Engineering
    Our in-house technical team developed fully coordinated façade designs, incorporating structural calculations, thermal modelling, and detailed interface coordination to ensure compliance and buildability from day one.
  • Procurement & Logistics
    We managed the complete supply chain, delivering system components and bespoke fabrications to suit the programme and restricted site conditions, minimising disruption and maximising efficiency.
  • Installation
    Our experienced installation teams delivered all façade elements safely, accurately, and to programme, maintaining exceptional standards across all visible and performance-critical areas.
  • Quality & Safety
    Robust QA procedures and uncompromising health and safety standards were implemented throughout the project, ensuring consistency, compliance, and peace of mind for the client.


Challenges Faced:

  • Managing complex façade interfaces across multiple systems
  • Working within a tightly sequenced programme
  • Maintaining premium architectural finishes within constrained urban site logistics


Results:

  • A visually striking, high-quality façade that enhances the overall architectural identity of Block E1
  • On-time delivery aligned with our programme and performance expectations
  • A trusted partnership approach that reinforced DMC Walling’s reputation as a reliable façade specialist for high-end residential developments
Full-service offerings
Environmentally Conscious
Strong partnerships